Carriageway Resurfacing/ Repair Works in Hounslow Road

I received the following this morning regarding the above (only applies between Lansbury Avenue- Brainton Avenue):

“I am pleased to inform you that the above work is part of an approved maintenance programme for your area.

The work is due to commence on 19 November 2012 and should be completed within 5 nights. The work will be carried out between 7.30pm and 4.30am at night. The contractor will advise dates and any changes by the placing of signs in the road.

Traffic through the working area will be controlled by the Contractor’s traffic signals or stop-go boards.

Access to the business/properties within the resurfacing limits will be maintained as far as it is reasonably practical, and will be subject to the contractor’s traffic control. Unfortunately there will be delays. Emergency access will not be affected. Any road markings will be replaced as a separate operation as soon as possible.”